Last Updated 2/24/20

 

New Traffic Signals

 

Project Overview 

Building off Midtown Alliance and the City of Atlanta’s effort to create safe intersection crossings for people walking, biking, taking transit, driving, and using shareable mobility devices, this project will install three (3) new traffic signals at the following intersections:

  1. West Peachtree St and 13th Street
  2. Peachtree Street and 13th Street
  3. Juniper Street and 13th Street


The project scope includes new traffic signal equipment, mast arms and poles, ADA compliant ramps and crosswalks, as well as appropriate signage and lane markings for current and future bicycle facilities. Traffic signal warrant studies were conducted by Midtown Alliance and approved by the City of Atlanta in 2019. 


Project Funding

  • $600,000 in City of Atlanta Transportation Impact Fees
  • $150,000 Midtown Improvement District funds
  • Total funding: $750,000 


Design/Engineering

Project scoping is complete. The Design and Engineering phase will include:

  • City and stakeholder coordination
  • Survey and subsurface evaluations for signal locations 
  • Develop preliminary and final design plans
  • Cost estimating
  • Develop construction permitting documents

 

What’s Next?

Design and Engineering will continue into 2020.  Upon completion, the project is estimated to begin construction in early 2021. Please stay tuned for project updates! If you have general comments or questions, please contact Transportation@MidtownATL.com

 