Skip to Main Content

Under Construction

Monthly Projects Update: March 24, 2026

Each month, we provide a construction update on our current Capital Improvement projects. See what's happening as we give you more to love about Midtown.

Projects Currently Under Construction

Click the project name below to learn more!

1.  Juniper Complete Street

Construction of this mile-long public right-of-way project mobilized in May 2023. Contractors completed the majority of new curbs, sidewalks, ADA ramps, and other hardscape improvements on the east side of Juniper Street by February 2024. Contractors then shifted to the west side of Juniper Street and constructed similar improvements through end of 2024. In 2025, new streetlights were installed and energized by Georgia Power, and new traffic signal poles, mast arms, and signal heads were erected. Roadway pavement milling, repair, resurfacing, and new striping was completed in summer 2025, followed by installation of bike lane barriers and final signage. New stormwater planters were constructed and street trees and other project plantings were installed during landscape season. Traffic signals were activated in early 2026, and the project was substantially complete in early March 2026. Project closeout is underway. 

2. 15th Street Extension

Construction is well on its way to build a new multi-modal street connection to extend 15th Street from its current end point at West Peachtree Street two blocks west to Williams Street.

3. Spring Street Bicycle and Pedestrian Improvements Project

Project construction is underway to repurpose one southbound lane on Spring Street (US-19/SR-9) between Peachtree Road and 17th Street to accommodate wider sidewalks, ADA upgrades, street trees, pedestrian lighting, protected bicycle facilities, and traffic signal improvements.

4. 10th Street Bridge Multi-modal Connection Project

Construction is underway for multi-modal enhancements, including creation of a protected two-way bikeway on 10th Street Bridge spanning the Downtown Connector to link up the planned 10th Street multi-use path west of the Connector; a protected two-way bikeway on Williams Street to connect to planned bike facilities on Peachtree Place to the south and 12th Street to the north; enhanced and upgraded sidewalks and crosswalks; gateway features and lighting. Traffic operational improvements to manage traffic flow and address multi-modal conflicts will be implemented. Vehicular improvements include repaving, refreshed lane markings, new lane assignments, and improved signage. New landscaping is also planned, including new tree plantings between Williams Street and the east side of the Connector.

5. Piedmont Ave Complete Street

Construction began in June 2025 for safety and accessibility improvements to approximately 1.1 miles of Piedmont Avenue between Ponce De Leon and 15th Street. The project will construct a protected one-way northbound bike lane from Ponce to 14th St (the northbound complement to the Juniper Street southbound bike lane) and will replace the sidewalk on the east side of Piedmont between 14th St and 15th St with a multi-use path. Scope also includes upgraded sidewalks and ADA curb ramps; bulb-outs where possible to shorten pedestrian crossing distances; milling and resurfacing the roadway; stormwater planters; and new streetlights north of 14th St.

6. 98 14th Street Interim Improvements 

Contractor mobilized in late March 2026 to regrade the site to create an open multi-use lawn and walking paths around the perimeter, expected to be complete by mid-July 2026.

7. Sidewalk Improvements (Annual Program)

Pictured below is an example of sidewalk and ADA curb ramp repaired by our construction forces at Peachtree St and 8th St. Since November 2014, Midtown Alliance has performed $1,815,000 worth of sidewalk repairs in approximately 400 locations within and funded by the Midtown Improvement District (MID). Work includes replacing or grinding concrete, resetting pavers, new curb and ADA ramp upgrades, tree well expansions, and other sidewalk repairs to help maintain and improve pedestrian mobility in Midtown.

The program will continue in 2026 to address prioritized locations throughout the District.

Next Up for Construction

In March 2026, the City of Atlanta started construction of safety improvements and resurfacing on West Peachtree Street from Linden Ave to 11th St. Later in 2026, Midtown Alliance plans to seek construction bids for similar improvements on the remaining portion of West Peachtree Street from 11th to 17th St and Spring Street from 17th St to 3rd St.

On the Design Boards

Visit this page to learn more about other capital projects in the works, studies, enhancements and activation underway.

Our ongoing projects help keep Midtown safe, improve accessibility, and enhance our livability. Contact us with questions or feedback on these projects and construction updates.